01-Land preparation
02-Preparation of real architectural plans by architectural design offices (real executive plans of the building including architectural plan booklet and electrical and mechanical installation plan booklet)
03- Concluding a power of attorney contract for the execution of municipal works and the engineering system and obtaining a license and no violations and contractors with the engineering office
04- Concluding a contract with the engineering office to prepare municipal plans and engineering system
05-Preparation of real executive plans of the structure by the engineering office
06-Preparation of guard structure map by engineering office
07- Concluding a power of attorney contract for the implementation of administrative work, including water, electricity, gas, telecommunications, social security, and MAP with the engineering office.
08-Obtaining a building permit
09- Insuring the construction workshop
10- Demolition of the old building
11- Establishing a guard and equipping the workshop
12- Excavation
13-Execution of guard structure
14. Concrete except for Chinese molds
15-Reinforcement of the foundation
16-Concrete foundation
17- Execution of steel structure (skeleton welding)
18- Formatting floors
19- Concreting floors
20-Chinese blade
21-Gypsum soil
22- Water and sewage piping
23- Signing a contract for extinguishing and announcing fire and firefighting with fire service offices with the approval of the technical engineering office
24- Execution of gas extraction of units
25. Built-in electricity
26-Execution of sample unit
27- Rabitz classification (two groups – a common group and a group within the units)
28. Composition of facade windows and aluminum doors
29. Com metal doors and storage doors
30- Welding of trusses and telephoto
31- Obtaining the end of hardening work
32- Temporary welding between stairs and elevators
33- Execution of the view (main and sub view of one group and other views of another group – first the main view and then the other views should be executed)
34- Concluding an elevator contract with standard approval
35-Rainwater digging well
36. The slope of the roof is primary visogam
37-Izogam services
38- Obtaining water and sewage branches (in the number of units and a general number)
39- Obtaining power branches (in the number of units and a general number)
40- Drilling earth wells with the approval of the electricity company
41-Tile work
42-Preparing the floor of the units
43-Ceramic work
44-Plastering (groups should be the number of units in each floor)
45-Com the entrance doors of the units or install anti-theft doors
46 Facade windows and aluminum doors
47-Roof insulation
48. Skylight coupling for truss
49- Wooden doors of units
50. Cabinets and unit closets
51. Cabinets and decor
52 Stairs
53-Stair railing welding
54-Pilot and yard mosaic
55-Yard stone work
56. Painting and wallpaper
57- Installing windows and doors glass
58-Purchase and installation of valves and sanitary ware accessories from the agency (be sure to separate from the water plumber)
59-Electrical installations
60- Purchasing and installing the radiator package from the dealer (be sure to separate it from the water plumber)
61-Install the elevator
62- Installation of yard and parking doors
63- Preparing the ticket map only by a competent executing engineer
64- Releasing the quota of a competent executive engineer
65- Obtaining gas approvals and branches
66- Obtaining firefighting approval by the technical engineering office
67. End of operation
68- Concluding a power of attorney contract for the execution of document registration and document separation of units
69-Sale of units